Day 10 (11th June)

Yesterday was rest day, much needed after an exhausting 6 days last week

Our planned activities for today were checking and correcting the sag differential between the two cables by re-winching to tighten or loosen the cables as appropriate. The second¬†planned¬†task was pouring of the concrete infill slab at the far end of the bridge. Continue reading “Day 10 (11th June)”